Home › Laws by state › New Mexico

Is plug-in solar legal in New Mexico?

Bill stalled (likely refiled 2027) SB 157 (+ HM 38, SM 10)
  1. Introduced
  2. Passed one chamber
  3. Passed both chambers
  4. Signed
  5. In effect

The 2026 bill died at this stage; sponsors are expected to refile in 2027.

Not yet. New Mexico considered a plug-in solar bill (SB 157 (+ HM 38, SM 10)) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.
Max system sizeNo capsmallest tier: <=10 kW simplified
Electrician / permitPermit and inspectionutility rules apply
Tell the utility?Interconnection applicationtypical fee $150
CertificationUL 1741 inverterrequired by every utility

What this means for you

✓ What you can do

  • Apply for interconnection like any small generator (<=10 kW simplified), typical fee $150.
  • Use portable panels with a power station, never connected to house wiring, with no permission at all.
  • Install conventional rooftop or ground-mount solar through the standard interconnection process.

✕ Not yet / not allowed

  • Plug a grid-tied kit into an outlet without an interconnection agreement; it can breach your service terms.
  • Expect a permit or wiring exemption; none exists without a law.
  • Count on SB 157 this year: Introduced 1/26/2026 (30-day session); Action Postponed Indefinitely by Senate Committees' Committee; died; deferred to 2027.

What the rules say

New Mexico's SB 157 died in the 2026 short session; PNM interconnection rules apply.

What happened in 2026. SB 157: Introduced 1/26/2026 (30-day session); Action Postponed Indefinitely by Senate Committees' Committee; died; deferred to 2027.

Before you plug in: New Mexico checklist

  1. The rule that applies is New Mexico Public Regulation Commission's interconnection process: 17.9.568 NMAC (interconnection) / 17.9.570 NMAC (net metering).
  2. A plug-in kit falls in the smallest tier (<=10 kW simplified). $150 application fee (<=25 kW).
  3. Permits: CID electrical permit; 2020 NEC; homeowner permits allowed.
  4. Only consider kits with a UL 1741-listed inverter (UL 3700 preferred); a non-listed inverter will not be approved anywhere.
  5. What exports are worth: Monthly netting, excess at avoided cost (<=10 kW).
  6. If approval is slow or costly, a portable panel and power station (never connected to house wiring) needs no permission.
  7. Watch SB 157: Introduced 1/26/2026 (30-day session); Action Postponed Indefinitely by Senate Committees' Committee; died; deferred to 2027.

The rules in detail

New Mexico has no statute specific to plug-in solar (the only bill so far is SB 157 (+ HM 38, SM 10)). Average residential electricity price: 16.09¢ per kWh (EIA, July 2026).

  • Sponsor: Sens. Jeff Steinborn, Harold Pope.
  • Utilities: Delayed after utility concerns (NPR).

Your utility's rules in New Mexico

No utility in New Mexico publishes a rule that specifically allows or bans outlet-connected generation, so the general interconnection agreement is what applies. Here is what the largest residential utilities say and require.

UtilityResidential customersPublished position on plug-in kits
Public Service Co. of New Mexico 492,945 No specific statement.
Southwestern Public Service (Xcel) 100,540 No specific statement.
El Paso Electric (NM) 94,760 No specific statement.

Customer counts: EIA Form 861, 2024. Positions checked October 18, 2026.

Interconnection terms for a sub-1.2 kW system

RegulatorNew Mexico Public Regulation Commission.
Governing rule17.9.568 NMAC (interconnection) / 17.9.570 NMAC (net metering).
Smallest tier<=10 kW simplified; fee tier <=25 kW.
Application fee$150 application fee (<=25 kW).
Electrician / permitCID electrical permit; 2020 NEC; homeowner permits allowed.
Export compensationMonthly netting, excess at avoided cost (<=10 kW).
Electrical code2020 NEC (eff. 3/28/2023).
In practice
  • Died on 30-day-session germaneness; 2027 60-day session is a real opening.
  • $150 fee exceeds a decade of a 400 W kit's export value.

Plug-in solar bills in New Mexico, 2025–2026

BillSponsorStatusWhat it would do
SB 157Sens. Harold Pope and Jeff Steinborn (D)Introduced 1/26/2026 (30-day session); Action Postponed Indefinitely by Senate Committees' Committee; died; deferred to 2027.Use of Portable Solar Generation Devices (tracker: 1,920 W variant).

State incentives

  • Solar Market Development Tax Credit 10% up to $6,000 (EMNRD certification required).

Who is pushing for a law

  • Bright Saver
  • CCAE / Sierra Club Rio Grande (not confirmed)

Savings preview: 800 W kit in New Mexico

About 1120 kWh per year at 16.09¢/kWh, assuming a south-facing balcony or patio mount with typical shading losses.

Adjust for your setup →

≈ $180/year

Frequently asked questions

Is plug-in solar legal in New Mexico?

Not yet. New Mexico considered a plug-in solar bill (SB 157 (+ HM 38, SM 10)) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.

Do I need a permit or electrician for plug-in solar in New Mexico?

Default. Check with your local building department before you plug in.

Do I have to tell my utility in New Mexico?

Default. Plugging in a grid-tied kit without following this can breach your service agreement.

What can an 800 W plug-in kit save in New Mexico?

Roughly 1120 kWh and about $180 per year at New Mexico's average residential rate of 16.09¢/kWh, assuming a typical balcony or patio mount. See the calculator for your exact setup.

Sources

  1. ncelenviro.org
  2. npr.org
  3. nmlegis.gov
  4. regulations.justia.com
  5. Mike Holt NEC adoption list
  6. EIA Form 861 (2024)

Spotted a change in New Mexico's law? Tell us and we will update this page.