Is plug-in solar legal in Minnesota?

Bill stalled (likely refiled 2027) HF 3555 / SF 3873 / SF 4504
  1. Introduced
  2. Passed one chamber
  3. Passed both chambers
  4. Signed
  5. In effect

The 2026 bill died at this stage; sponsors are expected to refile in 2027.

Not yet. Minnesota considered a plug-in solar bill (HF 3555 / SF 3873 / SF 4504) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.
Max system sizeNo capsmallest tier: Certified inverter <=20 kW
Electrician / permitPermit and inspectionutility rules apply
Tell the utility?Interconnection applicationtypical fee $200
CertificationUL 1741 inverterrequired by every utility

What this means for you

✓ What you can do

  • Apply for interconnection like any small generator (Certified inverter <=20 kW), typical fee $200.
  • Use portable panels with a power station, never connected to house wiring, with no permission at all.
  • Install conventional rooftop or ground-mount solar through the standard interconnection process.

✕ Not yet / not allowed

  • Plug a grid-tied kit into an outlet without an interconnection agreement; it can breach your service terms.
  • Expect a permit or wiring exemption; none exists without a law.
  • Count on SF 3873 / HF 3555; folded into SF 4504 omnibus this year: SF 4504 passed Senate 5/12/2026; House never acted; sine die 5/18/2026; deferred to 2027.

What the rules say

Minnesota's 2026 bills did not pass; Xcel interconnection rules apply.

What happened in 2026. SF 3873 / HF 3555; folded into SF 4504 omnibus: SF 4504 passed Senate 5/12/2026; House never acted; sine die 5/18/2026; deferred to 2027.

Before you plug in: Minnesota checklist

  1. The rule that applies is Minnesota Public Utilities Commission's interconnection process: MN DIP (2019) Simplified Process.
  2. A plug-in kit falls in the smallest tier (Certified inverter <=20 kW). Xcel $200 cost-share fee (<=40 kW); munis $100-$125.
  3. Permits: Licensed electrician or homeowner with permit/inspection; 2026 NEC.
  4. Only consider kits with a UL 1741-listed inverter (UL 3700 preferred); a non-listed inverter will not be approved anywhere.
  5. What exports are worth: Retail-rate net metering <40 kW (Minn. Stat. 216B.164).
  6. If approval is slow or costly, a portable panel and power station (never connected to house wiring) needs no permission.
  7. Watch SF 3873 / HF 3555; folded into SF 4504 omnibus: SF 4504 passed Senate 5/12/2026; House never acted; sine die 5/18/2026; deferred to 2027.

The rules in detail

Minnesota has no statute specific to plug-in solar (the only bill so far is HF 3555 / SF 3873 / SF 4504). Average residential electricity price: 17.45¢ per kWh (EIA, July 2026).

  • Sponsor: Rep. Larry Kraft (HF 3555); Sen. Rob Kupec (SF 3873).

Your utility's rules in Minnesota

No utility in Minnesota publishes a rule that specifically allows or bans outlet-connected generation, so the general interconnection agreement is what applies. Here is what the largest residential utilities say and require.

UtilityResidential customersPublished position on plug-in kits
Xcel Energy (NSP-Minnesota) 1,230,057 No specific statement.
Connexus Energy 134,095 No specific statement. source
Minnesota Power 125,896 No specific statement. source
Dakota Electric 108,097 No specific statement.

Customer counts: EIA Form 861, 2024. Positions checked October 18, 2026.

Interconnection terms for a sub-1.2 kW system

RegulatorMinnesota Public Utilities Commission.
Governing ruleMN DIP (2019) Simplified Process.
Smallest tierCertified inverter <=20 kW.
Application feeXcel $200 cost-share fee (<=40 kW); munis $100-$125.
Electrician / permitLicensed electrician or homeowner with permit/inspection; 2026 NEC.
Export compensationRetail-rate net metering <40 kW (Minn. Stat. 216B.164).
Electrical code2026 NEC (eff. 8/17/2026).
In practice
  • Most generous export compensation in scope.
  • 2026 NEC adopted Aug 2026 removes the electrician objection.

Plug-in solar bills in Minnesota, 2025–2026

BillSponsorStatusWhat it would do
SF 3873 / HF 3555; folded into SF 4504 omnibusSen. Rob Kupec (DFL-Moorhead); Rep. Larry Kraft (DFL-St. Louis Park); omnibus Sen. Nick FrentzSF 4504 passed Senate 5/12/2026; House never acted; sine die 5/18/2026; deferred to 2027.<=1,200 W NRTL-certified, may connect to storage; Sen. Rarick (R, electrician): 'too early'.

State incentives

  • Sales-tax exemption Minn. Stat. 297A.67 subd. 29.
  • Xcel Solar*Rewards (interconnected, >=0.5 kW).

Who is pushing for a law

  • Vote Solar (Patty O'Keefe)
  • Fresh Energy
  • MnSEIA
  • Bright Saver

Savings preview: 800 W kit in Minnesota

About 845 kWh per year at 17.45¢/kWh, assuming a south-facing balcony or patio mount with typical shading losses.

Adjust for your setup →

≈ $147/year

Frequently asked questions

Is plug-in solar legal in Minnesota?

Not yet. Minnesota considered a plug-in solar bill (HF 3555 / SF 3873 / SF 4504) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.

Do I need a permit or electrician for plug-in solar in Minnesota?

Default. Check with your local building department before you plug in.

Do I have to tell my utility in Minnesota?

Default. Plugging in a grid-tied kit without following this can breach your service agreement.

What can an 800 W plug-in kit save in Minnesota?

Roughly 845 kWh and about $147 per year at Minnesota's average residential rate of 17.45¢/kWh, assuming a typical balcony or patio mount. See the calculator for your exact setup.

Sources

  1. ncel.net
  2. Bright Saver state tracker
  3. mprnews.org
  4. revisor.mn.gov
  5. mn.gov
  6. Mike Holt NEC adoption list
  7. EIA Form 861 (2024)

Spotted a change in Minnesota's law? Tell us and we will update this page.