Is plug-in solar legal in Arizona?

Bill stalled (likely refiled 2027) HB 2843 / SB 1606
  1. Introduced
  2. Passed one chamber
  3. Passed both chambers
  4. Signed
  5. In effect

The 2026 bill died at this stage; sponsors are expected to refile in 2027.

Not yet. Arizona considered a plug-in solar bill (HB 2843 / SB 1606) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.
Max system sizeNo capsmallest tier: Level 1 Super Fast Track: inverter-based <=20 kW certified equipment, 14-day review
Electrician / permitPermit and inspectionutility rules apply
Tell the utility?Interconnection applicationOnly if in approved tariff (R14-2-2614(B)(3)); amounts not retrieved
CertificationUL 1741 inverterrequired by every utility

What this means for you

✓ What you can do

  • Apply for interconnection like any small generator (Level 1 Super Fast Track: inverter-based <=20 kW certified equipment, 14-day review), Only if in approved tariff (R14-2-2614(B)(3)); amounts not retrieved.
  • Use portable panels with a power station, never connected to house wiring, with no permission at all.
  • Install conventional rooftop or ground-mount solar through the standard interconnection process.

✕ Not yet / not allowed

  • Plug a grid-tied kit into an outlet without an interconnection agreement; it can breach your service terms.
  • Expect a permit or wiring exemption; none exists without a law.
  • Count on SB 1606 this year: Did not advance (2026); deferred to 2027.

What the rules say

Arizona's 2026 bills died after utilities objected; APS/SRP interconnection rules still apply.

What happened in 2026. SB 1606: Did not advance (2026); deferred to 2027.

Before you plug in: Arizona checklist

  1. The rule that applies is Arizona Corporation Commission (APS, TEP, UNS, co-ops); SRP self-governed's interconnection process: A.A.C. R14-2-2601 et seq. (2020).
  2. A plug-in kit falls in the smallest tier (Level 1 Super Fast Track: inverter-based <=20 kW certified equipment, 14-day review). Only if in approved tariff (R14-2-2614(B)(3)); amounts not retrieved.
  3. Permits: No statewide NEC; municipal permits/inspection required for PTO.
  4. Only consider kits with a UL 1741-listed inverter (UL 3700 preferred); a non-listed inverter will not be approved anywhere.
  5. What exports are worth: Net billing at Resource Comparison Proxy (APS ~5.55 c, TEP ~4.6 c, SRP ~1.9 c/kWh) after interconnection.
  6. If approval is slow or costly, a portable panel and power station (never connected to house wiring) needs no permission.
  7. Watch SB 1606: Did not advance (2026); deferred to 2027.

The rules in detail

Arizona has no statute specific to plug-in solar (the only bill so far is HB 2843 / SB 1606). Average residential electricity price: 15.38¢ per kWh (EIA, July 2026).

  • Utilities: Vote delayed after utility opposition (NPR Mar 2026).

Your utility's rules in Arizona

No utility in Arizona publishes a rule that specifically allows or bans outlet-connected generation, so the general interconnection agreement is what applies. Here is what the largest residential utilities say and require.

UtilityResidential customersPublished position on plug-in kits
Arizona Public Service 1,256,120 No specific statement.
Salt River Project 1,053,407 No specific statement (self-regulated political subdivision).
Tucson Electric Power 412,747 No specific statement.
UNS Electric 95,191 No specific statement.

Customer counts: EIA Form 861, 2024. Positions checked October 18, 2026.

Interconnection terms for a sub-1.2 kW system

RegulatorArizona Corporation Commission (APS, TEP, UNS, co-ops); SRP self-governed.
Governing ruleA.A.C. R14-2-2601 et seq. (2020).
Smallest tierLevel 1 Super Fast Track: inverter-based <=20 kW certified equipment, 14-day review.
Application feeOnly if in approved tariff (R14-2-2614(B)(3)); amounts not retrieved.
Electrician / permitNo statewide NEC; municipal permits/inspection required for PTO.
Export compensationNet billing at Resource Comparison Proxy (APS ~5.55 c, TEP ~4.6 c, SRP ~1.9 c/kWh) after interconnection.
Electrical codeNone statewide (local adoption).
In practice
  • Phoenix metro splits between APS (ACC rules) and SRP (own rules, ~1.9 c export credit).
  • No statewide electrical code: permittability depends on city/county NEC edition.

Plug-in solar bills in Arizona, 2025–2026

BillSponsorStatusWhat it would do
SB 1606Sen. Kuby with Sens. Alston, Diaz, Epstein, Gabaldon, Miranda, Ortiz, Sundareshan, Rep. GarciaDid not advance (2026); deferred to 2027.<=1,200 W, standard 120 V outlet, NRTL-certified; bars public power entities and public service corporations from requiring approval/fees.

State incentives

  • A.R.S. 43-1083 credit 25% up to $1,000 (owner-installed devices).
  • TPT exemption for solar devices via registered retailers; plug-in eligibility untested.

Who is pushing for a law

  • Solar United Neighbors Arizona
  • Western Resource Advocates
  • Bright Saver

Savings preview: 800 W kit in Arizona

About 1120 kWh per year at 15.38¢/kWh, assuming a south-facing balcony or patio mount with typical shading losses.

Adjust for your setup →

≈ $172/year

Frequently asked questions

Is plug-in solar legal in Arizona?

Not yet. Arizona considered a plug-in solar bill (HB 2843 / SB 1606) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.

Do I need a permit or electrician for plug-in solar in Arizona?

Default rules apply. Check with your local building department before you plug in.

Do I have to tell my utility in Arizona?

Bill: no prior approval; default rules apply now. Plugging in a grid-tied kit without following this can breach your service agreement.

What can an 800 W plug-in kit save in Arizona?

Roughly 1120 kWh and about $172 per year at Arizona's average residential rate of 15.38¢/kWh, assuming a typical balcony or patio mount. See the calculator for your exact setup.

Sources

  1. azleg.gov
  2. npr.org
  3. Bright Saver state tracker
  4. azleg.gov
  5. law.cornell.edu
  6. azleg.gov
  7. Mike Holt NEC adoption list
  8. EIA Form 861 (2024)

Spotted a change in Arizona's law? Tell us and we will update this page.