Home › Laws by state › Florida

Is plug-in solar legal in Florida?

No specific law

No plug-in solar bill has been introduced in this state.

Florida has no plug-in solar law. Plugging a kit into an outlet falls under your utility's interconnection rules, which usually require approval.
Max system sizeNo capsmallest tier: Tier 1 <=10 kW AC: no application fee, no insurance
Electrician / permitPermit and inspectionutility rules apply
Tell the utility?Interconnection applicationtypical fee $0
CertificationUL 1741 inverterrequired by every utility

What this means for you

✓ What you can do

  • Apply for interconnection like any small generator (Tier 1 <=10 kW AC: no application fee, no insurance), typical fee $0.
  • Use portable panels with a power station, never connected to house wiring, with no permission at all.
  • Install conventional rooftop or ground-mount solar through the standard interconnection process.

✕ Not yet / not allowed

  • Plug a grid-tied kit into an outlet without an interconnection agreement; it can breach your service terms.
  • Expect a permit or wiring exemption; none exists without a law.
  • Count on a law soon: no plug-in solar bill has been filed.

What the rules say

Florida has no plug-in solar law or bill; standard interconnection rules apply.

No law doesn't mean no rules. In Florida, a kit that pushes power back into your home wiring is treated like any other grid-connected generator. Most utilities require an interconnection application, and plugging in without one can breach your service agreement. Off-grid use (panels charging a battery that powers devices directly) avoids this entirely.

Before you plug in: Florida checklist

  1. The rule that applies is Florida Public Service Commission (IOUs only)'s interconnection process: Rule 25-6.065 F.A.C. (2008).
  2. A plug-in kit falls in the smallest tier (Tier 1 <=10 kW AC: no application fee, no insurance). $0 Tier 1; Tier 2 $400 (FPL) / $240 (Duke) + $1M insurance.
  3. Permits: Florida Building Code permit + AHJ inspection; 2020 NEC.
  4. Only consider kits with a UL 1741-listed inverter (UL 3700 preferred); a non-listed inverter will not be approved anywhere.
  5. What exports are worth: Retail net metering with annual avoided-cost true-up (IOUs); munis/co-ops vary.
  6. If approval is slow or costly, a portable panel and power station (never connected to house wiring) needs no permission.
  7. No plug-in solar bill has been filed yet; the nearby states that passed laws in 2026 are the template to expect.

The rules in detail

Florida has no statute specific to plug-in solar. Average residential electricity price: 15.03¢ per kWh (EIA, July 2026).

  • Utilities: FPL/Duke interconnection rules apply.

Your utility's rules in Florida

No utility in Florida publishes a rule that specifically allows or bans outlet-connected generation, so the general interconnection agreement is what applies. Here is what the largest residential utilities say and require.

UtilityResidential customersPublished position on plug-in kits
Florida Power & Light 5,236,277 No specific statement; 'We must preapprove your system before installation.'. source
Duke Energy Florida 1,793,067 No specific statement.
Tampa Electric 757,280 No specific statement.
JEA (muni) 470,564 No specific statement; not bound by Rule 25-6.065.

Customer counts: EIA Form 861, 2024. Positions checked October 18, 2026.

Interconnection terms for a sub-1.2 kW system

RegulatorFlorida Public Service Commission (IOUs only).
Governing ruleRule 25-6.065 F.A.C. (2008).
Smallest tierTier 1 <=10 kW AC: no application fee, no insurance.
Application fee$0 Tier 1; Tier 2 $400 (FPL) / $240 (Duke) + $1M insurance.
Electrician / permitFlorida Building Code permit + AHJ inspection; 2020 NEC.
Export compensationRetail net metering with annual avoided-cost true-up (IOUs); munis/co-ops vary.
Electrical code2020 NEC (eff. 12/31/2023; 2023 update pending).
In practice
  • Tier 1 is free but FPL must preapprove before installation and assumes a permitted hard-wired system.
  • ~25% on munis/co-ops not bound by PSC rule.

State incentives

  • Sales-tax exemption F.S. 212.08(7)(hh) for FSEC-certified equipment (component-level).
  • Property-tax exemption.

Who is pushing for a law

  • Third Act Florida
  • Solar United Neighbors Florida
  • Florida Conservation Voters

Savings preview: 800 W kit in Florida

About 928 kWh per year at 15.03¢/kWh, assuming a south-facing balcony or patio mount with typical shading losses.

Adjust for your setup →

≈ $139/year

Frequently asked questions

Is plug-in solar legal in Florida?

Florida has no plug-in solar law. Plugging a kit into an outlet falls under your utility's interconnection rules, which usually require approval.

Do I need a permit or electrician for plug-in solar in Florida?

Default. Check with your local building department before you plug in.

Do I have to tell my utility in Florida?

Default tariff applies. Plugging in a grid-tied kit without following this can breach your service agreement.

What can an 800 W plug-in kit save in Florida?

Roughly 928 kWh and about $139 per year at Florida's average residential rate of 15.03¢/kWh, assuming a typical balcony or patio mount. See the calculator for your exact setup.

Sources

  1. Bright Saver state tracker
  2. Exact Solar newsletter
  3. flrules.org
  4. theinvadingsea.com
  5. Bright Saver state tracker
  6. Mike Holt NEC adoption list
  7. EIA Form 861 (2024)