Is plug-in solar legal in Delaware?

Bill stalled (likely refiled 2027) SB 270
  1. Introduced
  2. Passed one chamber
  3. Passed both chambers
  4. Signed
  5. In effect

The 2026 bill died at this stage; sponsors are expected to refile in 2027.

Not yet. Delaware considered a plug-in solar bill (SB 270) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.
Max system sizeNo capsmallest tier: Level 1 <=10 kW certified inverter
Electrician / permitPermit and inspectionutility rules apply
Tell the utility?Interconnection applicationtypical fee $1,515
CertificationUL 1741 inverterrequired by every utility

What this means for you

✓ What you can do

  • Apply for interconnection like any small generator (Level 1 <=10 kW certified inverter), typical fee $1,515.
  • Use portable panels with a power station, never connected to house wiring, with no permission at all.
  • Install conventional rooftop or ground-mount solar through the standard interconnection process.

✕ Not yet / not allowed

  • Plug a grid-tied kit into an outlet without an interconnection agreement; it can breach your service terms.
  • Expect a permit or wiring exemption; none exists without a law.
  • Count on SB 270 this year: Introduced 3/26/2026, Senate Environment, Energy & Transportation; no hearing; deferred to 2027.

What the rules say

Delaware's SB 270 (introduced Mar 26, 2026) would allow 800 W per meter with online registration; it has not passed.

What happened in 2026. SB 270: Introduced 3/26/2026, Senate Environment, Energy & Transportation; no hearing; deferred to 2027.

Before you plug in: Delaware checklist

  1. The rule that applies is Delaware Public Service Commission (Delmarva); DEC/munis self-set within 26 Del. C. 1014's interconnection process: Delmarva Delaware Interconnection Standards (PSC Order 7984, 2011; IREC model).
  2. A plug-in kit falls in the smallest tier (Level 1 <=10 kW certified inverter). Not located (gap); Smyrna muni $1,515.
  3. Permits: State Fire Marshal adopts NEC; electrical permits/inspections required.
  4. Only consider kits with a UL 1741-listed inverter (UL 3700 preferred); a non-listed inverter will not be approved anywhere.
  5. What exports are worth: Full retail net metering <=25 kW residential.
  6. If approval is slow or costly, a portable panel and power station (never connected to house wiring) needs no permission.
  7. Watch SB 270: Introduced 3/26/2026, Senate Environment, Energy & Transportation; no hearing; deferred to 2027.

The rules in detail

Delaware has no statute specific to plug-in solar (the only bill so far is SB 270). Average residential electricity price: 18.48¢ per kWh (EIA, July 2026).

  • Exported power: Bill: exempt unless customer seeks net metering.

Your utility's rules in Delaware

No utility in Delaware publishes a rule that specifically allows or bans outlet-connected generation, so the general interconnection agreement is what applies. Here is what the largest residential utilities say and require.

UtilityResidential customersPublished position on plug-in kits
Delmarva Power 301,950 No specific statement; Level 1 = 'lab certified, inverter-based systems with a nameplate capacity of 10 kW or less'. source
Delaware Electric Cooperative 104,839 No specific statement.
City of Dover 21,601 No specific statement.

Customer counts: EIA Form 861, 2024. Positions checked October 18, 2026.

Interconnection terms for a sub-1.2 kW system

RegulatorDelaware Public Service Commission (Delmarva); DEC/munis self-set within 26 Del. C. 1014.
Governing ruleDelmarva Delaware Interconnection Standards (PSC Order 7984, 2011; IREC model).
Smallest tierLevel 1 <=10 kW certified inverter.
Application feeNot located (gap); Smyrna muni $1,515.
Electrician / permitState Fire Marshal adopts NEC; electrical permits/inspections required.
Export compensationFull retail net metering <=25 kW residential.
Electrical code2023 NEC (eff. 1/1/2026 per Mike Holt).
In practice
  • Only US bill at an 800 W cap; would still require registration.
  • No sales tax; Green Energy grant unavailable to DIY kits.

Plug-in solar bills in Delaware, 2025–2026

BillSponsorStatusWhat it would do
SB 270Sen. Stephanie Hansen (SD10); Reps. Burns, Heffernan; cosponsors Cruce, Hoffner, Pinkney, Sokola, Lambert, Morrison, RomerIntroduced 3/26/2026, Senate Environment, Energy & Transportation; no hearing; deferred to 2027.800 W per-meter cap (lowest in US); exempt unless net metering; utility online registry by 1/15/2027; DESEU safety study by 1/1/2027.

State incentives

  • Green Energy Program: Delmarva $0.70/W to $6,000, DEC $0.35/W (participating contractor required).
  • No sales tax.

Who is pushing for a law

  • Bright Saver (no named DE group confirmed)

Savings preview: 800 W kit in Delaware

About 864 kWh per year at 18.48¢/kWh, assuming a south-facing balcony or patio mount with typical shading losses.

Adjust for your setup →

≈ $160/year

Frequently asked questions

Is plug-in solar legal in Delaware?

Not yet. Delaware considered a plug-in solar bill (SB 270) that did not pass in 2026; a new version is expected. Until then, utility interconnection rules apply.

Do I need a permit or electrician for plug-in solar in Delaware?

Default rules apply. Check with your local building department before you plug in.

Do I have to tell my utility in Delaware?

Not fully settled. Bill: utility online registration by 2027-01-15; exempt from interconnection unless net metering sought

What can an 800 W plug-in kit save in Delaware?

Roughly 864 kWh and about $160 per year at Delaware's average residential rate of 18.48¢/kWh, assuming a typical balcony or patio mount. See the calculator for your exact setup.

Sources

  1. legis.delaware.gov
  2. Bright Saver state tracker
  3. energizedelaware.org
  4. Mike Holt NEC adoption list
  5. EIA Form 861 (2024)

Spotted a change in Delaware's law? Tell us and we will update this page.